Monday, April 12, 2010

CAPITAL PROJECTS: UNITS/DECKS

Unit Painting
We will begin Phase 2 of our painting cycle. The schedule below lists the cul-de-sacs and respective dates [we will keep you apprised on our blog if rain dates are necessary:
#44 through 46 4/12 - 4/23 Completed 4/20/2010
#48 through 58 4/26 - 5/07 Started wood replacment 4/18/2010, Completed 5/12
#60 through 70 5/10 - 5/21 Prep completed 5/14, painting 5/16-5/20
#63 through 77 5/24 - 6/04 Prep started 5/16 Completed 06/04
#79 through 89 6/07 - 6/18 Prep started 06/01 Completed 6/12
#91 through 97 6/21 - 7/08 Prep started 06/14 Completed 06/28
#99 through 105 7/12 - 7/23 Prep to start 06/08 Completed 07/02
Touch Up completed 07/06 and 07/07

For only units that are being painted during this phase, we will be inspecting garage doors and unit owners will be advised in writing of door or panel replacements that are necessary.

DECKS
The following decks will be replaced this year: 39, 57, 80, 99, and 123. There is some paint work that also needs to be completed from last year. This will finally complete our Trek replacement for all decks.