Tuesday, May 19, 2009

Unit Painting To Start

Phase I to paint unit structures in Old Towne will begin with wood prep and paint at the pool house on Tuesday, May 26th. Then, we are anticipating a start date of June 1st as noted on the tentative schedule listed. Work is predicated on weather et al, therefore, Palmer Property Management will apprise unit owners of painting schedule. If unit owners have any questions or comments before or during the painting duration, please contact Jennifer at Palmer.

Tentative Schedule as of 6/11:
May 26th Pool House - Completed
June 1st Units 31-41 - Should be finished Mon 6/15
June 15th Units 53-61 - Will begin wood prep Mon 6/15
June 29th Units 107-117
July 13th Units 119-129
July 27th Units 131-157